‘West Hartford’ Sign Installed as Park Road Reopens, Detours Removed

Published On: August 23, 2019Categories: Government
Carbonatix Pre-Player Loader

Audio By Carbonatix

The new 'West Hartford' sign has been installed, welcoming drivers exiting I-84 at Exit 43. Courtesy photo

Phase 6 of the Park Road construction project, which began in late July, was completed Friday and the busy West Hartford road has been reopened to traffic.

Traffic flows in both directions on Park Road between the I-84 ramps and Trout Brook Drive. LiveCam as of Aug. 23, 3:10 p.m.

By Ronni Newton

The most disruptive stage of construction on Park Road at Trout Brook Drive and I-84 in West Hartford has come to an end, and Assistant Town Engineer Greg Sommer said Friday afternoon that the road has been completed reopened in all directions and detour signs have been removed.

“It’s fully open to traffic,” he said.

The project is not 100 percent complete, and raised utility structures remain in the project area, Sommer said, requiring motorists to still use extra caution. The roadway was intentionally paved a few inches low to accommodate a final course of pavement which should be installed in the middle of September.

That paving will take place overnight, and should take no more than two nights, Sommer said.

A new gateway sign now welcomes motorists to West Hartford from the off ramp for I-84 at Exit 43.

Sommer said additional landscaping will be installed – trees behind the sign as well as planters – in mid-September. Flags will fly from the flagpoles behind the sign as soon as the wiring for the illumination has been completed.

In addition to the final course of pavement, Sommer said that other remaining work includes landscaping of the project area, which should be completed during September and October.

“We will continue to tweak the traffic signals as regular flow of traffic returns,” he added.

Any activities in the future should cause only minor and temporary traffic disruption.

“This is an exciting milestone,” Sommer said. The project was completed on schedule.

“We didn’t have any weather issues, despite the recent storm events,” he said.

The approximately $6.8 million project began on Sept. 19, 2017, and was administered by the Town of West Hartford, with construction inspection services provided by Weston and Sampson Engineers, Inc. and oversight by the Office of Construction, District 1, Rocky Hill. Paramount Construction is the primary contractor. Federal funds have provided 80 percent of the costs, with the state and town each providing 10 percent.

Like what you see here? Click here to subscribe to We-Ha’s newsletter so you’ll always be in the know about what’s happening in West Hartford!

5 Comments

  1. Mike August 24, 2019 at 3:24 PM - Reply

    Who designed that West Hartford sign??? Horrible, it looks as if one is entering a playground.

  2. M August 25, 2019 at 7:33 AM - Reply

    The old West Hartford sign was much nicer!

  3. Bob August 25, 2019 at 4:15 PM - Reply

    Awful design. I was encouraged seeing the stone wall erected, but the colors do not go with it at all. This isn’t Six Flags.

  4. npv August 25, 2019 at 4:22 PM - Reply

    seems more than ok with me… I like it. Put some plants in and flags — looks great

  5. Mark Schoell August 28, 2019 at 9:38 AM - Reply

    UGLY
    doesn’t fit my image of West Hartford

Leave A Comment